Queensland's $139.5B Infrastructure Pipeline: Insights from the 2026 Major Projects Pipeline Report

Writer: Tahnia Miller
Tahnia Miller
10 hours ago
2 min read

Queensland's infrastructure pipeline continues to grow, with $139.5 billion in major projects identified in the Queensland Major Contractors Association's (QMCA) 2026 Major Projects Pipeline Report. However, while the scale of investment presents significant opportunities for the industry, the report highlights some important challenges around workforce capacity, productivity and project delivery.


Here's a look at the key findings.


Can We Deliver?


The 2026 pipeline spans 371 projects across Queensland, with investment split relatively evenly between the public and private sectors. Public projects account for $70.9 billion across 221 projects, while private investment makes up $68.8 billion across 150 projects.


Many projects are working towards the 2032 Olympic and Paralympic Games deadline.


The expansion of the pipeline is being driven by unfunded projects, highlighting uncertainty around which projects will progress into construction. The peak of funded work has shifted to FY29, when activity is projected to reach $20.6 billion, 32% higher than previous projections.


Workforce Demand Set to Increase


Delivering the full pipeline will require an average of 21,400 workers in FY27, rising to more than 39,000 through FY29 and FY30.


Electricity projects are expected to account for the largest share of average workforce demand over the next five years, followed by transport. The 2032 Games will also be a significant driver, accounting for an estimated 14 - 19% of average labour demand.


Queensland's construction workforce has grown, with approximately 285,785 people employed in February 2026, the heavy and civil engineering subsector accounted for around 32,400 of these workers.


Project Delays and Rising Delivery Costs


Workforce availability isn't the only challenge. Higher diesel prices are flowing through to plant, road freight, concrete deliveries, earthworks and regional logistics, adding further pressure to project costs.


Procurement and approvals are also contributing to delays. Complex tendering processes can add up to 12 months to tender-to-award timeframes, while extended environmental approvals continue to hold projects in pre-construction.


The impact is already being felt. In FY26, $3.5 billion less work was delivered across 15 fewer projects than projected, contributing to an estimated $966.3 million loss in Queensland economic activity and 4,523 jobs impacted.


Productivity and Modern Methods of Construction


The report identifies productivity as a major opportunity for the industry. Although engineering construction productivity has shown some improvement, it remains below the 2011 - 2016 peak.


QMCA highlights Modern Methods of Construction, including standardised designs, off-site pre-assembly and more efficient use of materials and equipment, as ways to improve productivity and reduce reliance on site labour.


Applied systematically across the pipeline, these approaches could deliver potential cost savings of $4 - 8 billion, alongside a reduction in site labour demand of up to 30%.


What Does This Mean for the Industry?


Queensland has a substantial pipeline of infrastructure work ahead, but delivering it will require more than investment alone.


Building workforce capacity, improving productivity, addressing procurement and approval bottlenecks, and creating greater certainty around project delivery will all be important.


Collaboration will be critical to ensuring Queensland has the people, materials and capability needed to turn the pipeline into completed infrastructure, both ahead of 2032 and beyond.


To see the full report, visit the QMCA website.