Queensland Construction Productivity Code 2026: What You Need to Know

The Queensland Government has released the Queensland Construction Productivity Code 2026 (the Code), setting new expectations for Queensland-funded construction projects, with a focus on delivering value for taxpayers and maintaining safe, productive, lawful and respectful workplaces.
The Code complements the existing Queensland Procurement Policy 2026 and introduces clearer requirements around workplace relations, project delivery and accountability for contractors involved in publicly funded construction work.
Here's what businesses operating across Queensland's civil infrastructure sector need to know.
What does the Code cover?
At its core, the Code aims to support more productive and efficient project delivery while ensuring appropriate workplace standards are maintained.
Its key objectives include:
Delivering better value for Queenslanders through projects completed on time and within budget.
Maintaining safe workplaces and strong work health and safety practices.
Promoting lawful and respectful workplace relations.
Improving project, workforce and contract management.
Protecting freedom of association and lawful right of entry.
Encouraging early resolution and reporting of workplace issues that could affect project delivery.
Establishing clear accountability for client agencies and principal contractors.
Compliance is an ongoing condition of participation in Queensland Government-funded construction projects.
When does the Code apply?
The Code applies to Queensland State Government-funded construction work valued at more than $150 million, where an expression of interest (EOI) or request for tender (RFT) is issued on or after 17 November 2026.
It applies to all parties participating in on-site activities, while projects valued below $150 million may also be brought under the requirements with approval from the Responsible Minister.
Importantly, privately funded construction is excluded, as is work undertaken using the Queensland Government's own workforce through entities such as RoadTek and QBuild. Local councils engaged to undertake work on behalf of the Queensland Government are also excluded.
Workplace Relations Management Plans
One of the key requirements introduced by the Code is the Workplace Relations Management Plan (WRMP).
Successful contractors must prepare a compliant WRMP before a contract is awarded. The plan outlines how labour sourcing, productivity, safety and workplace relations will be managed to support safe and efficient project delivery.
Tenderers aren't required to submit a full WRMP during the initial EOI or tender response stage. Instead, they must provide a written commitment confirming they understand the requirements, will comply with the Code and will prepare a compliant plan if shortlisted or invited to progress to the next procurement stage.
Where there is no shortlisting or subsequent tender stage, the successful tenderer must submit its WRMP before the contract is awarded or entered into.
QMCA welcomes the Code
The Queensland Major Contractors Association (QMCA) has welcomed the introduction of the Code, with CEO Andrew Chapman highlighting the need for greater consistency and accountability across the industry.
"QMCA and our members have been calling for a stronger, more consistent framework for years. This Code is an important step towards establishing a level playing field, with clear expectations and accountability for all parties."
With the Code now in place, contractors and businesses involved in Queensland's publicly funded infrastructure projects will need to understand how the new requirements affect their procurement processes, workforce planning and project delivery obligations.